Plain explanation
Under §9 (2) EEG 2023, a system with an installed power of 25 kW up to under 100 kW must have equipment that lets the grid operator reduce its feed-in remotely, until a smart meter (iMSys) and control box are installed and the grid operator has tested them. Below 25 kW that extra device isn't needed, but the 60 % feed-in cap for tariff systems still applies. The Clearingstelle EEG|KWKG, the official body that settles EEG questions, says 'installed power' for solar means the rated DC module power (kWp). The inverter rating doesn't count, because the inverter is not part of the 'Anlage' under the EEG. §9 (3) adds the trap: several solar systems on the same plot or building count as one system for this test if they are commissioned within 12 consecutive calendar months. A fence added within that window is added to the roof system. Plug-in devices up to 2 kW of modules and 800 VA of inverter power are left out of that sum. Separately, §9 (1) requires the whole system to be controllable by the grid operator once the smart meter and control box are in, so extra microinverters must be controllable too. Not legal advice. Some grid operators still read inverter kW. If yours does, point them to the Clearingstelle answer. Other inverter-side rules in the grid operator's connection conditions were not checked here.
Steps from the source
- Add up the module kWp of everything on the same plot or building commissioned within 12 consecutive calendar months
- Below 25 kWp: no remote-control device under §9 (2) Nr. 2, but the 60 % feed-in cap still applies to tariff systems until the smart meter is in and tested
- If you add modules later, register the extension with the grid operator and in the Marktstammdatenregister
- Plan any add-on inverters so the grid operator can control them once the smart meter and control box arrive (§9 (1))
- If the grid operator counts inverter kW, send them the Clearingstelle answer on 'installierte Leistung'
"Auf die Wechselrichterleistung kommt es dagegen nicht an, da diese schon nicht zur Anlage i.S.d. EEG gehören"
Word for word from the source.
Source
Where installers ask this
General guidance based on the manufacturer's manual or the named source. Always follow the current manual for your exact model and your national code. DC and AC electrical work is for qualified installers only. Not affiliated with or endorsed by any brand named; trademarks belong to their owners.