Ask a question
QS-019 · Grid voltage & grid connection

SMA event 101/301 grid voltage too high. Is it the inverter or the grid?

The short answer
Check grid voltage at the connection point; outside range = grid operator, in range = SMA Service.

Plain explanation

From the SMA manual for the Sunny Boy: Check grid voltage at connection point. If outside → grid operator. The rest of the checklist is below; work through it in order. Installer only: DC and AC work on a live PV system is dangerous, so owners should note the code and call their installer. Grid limits depend on your country, so check your national code and grid operator rules.

Steps from the source

  1. Check grid voltage at connection point
  2. If outside → grid operator
  3. If in range → SMA Service

Source

SMA Sunny Boy 3.0-5.0 Operating Manual (SB30-50-1AV-40-BE-en-10), §12.2 p64files.sma.de ↗

Where installers ask this

General guidance based on the manufacturer's manual or the named source. Always follow the current manual for your exact model and your national code. DC and AC electrical work is for qualified installers only. Not affiliated with or endorsed by any brand named; trademarks belong to their owners.

Get new answers and videos

We only use your email for these updates. We never sell it or give it to others for their own use. Details in our privacy notice.