Enphase consumption graph mirrors production. CT the wrong way round?

The short answer
Likely CT polarity: check phases in the graph and reverse CT polarity in the portal if needed.

Plain explanation

From the Enphase manual for the IQ Gateway + CTs: Check CT polarity (Graph > Show phases). Check load type. The rest of the checklist is below; work through it in order. Installer only: DC and AC work on a live PV system is dangerous, so owners should note the code and call their installer.

Steps from the source

  1. Check CT polarity (Graph > Show phases)
  2. Check load type
  3. Installer reverses CT polarity in portal
  4. Change meter start date

Source

Enphase Solar Troubleshooting Guide ING-00061-2.0 (2025-08-14), p19-22enphase.com ↗

Where installers ask this

General guidance based on the manufacturer's manual or the named source. Always follow the current manual for your exact model and your national code. DC and AC electrical work is for qualified installers only. Not affiliated with or endorsed by any brand named; trademarks belong to their owners.

Get new answers and videos

We only use your email for these updates. We never sell it or give it to others for their own use. Details in our privacy notice.