Make sure PE is connected to the inverter.
Plain explanation
From the SMA manual for the Sunny Boy: Installer ensures PE connected. Installer only: DC and AC work on a live PV system is dangerous, so owners should note the code and call their installer.
Steps from the source
- Installer ensures PE connected
Source
SMA Sunny Boy 3.0-5.0 Operating Manual (SB30-50-1AV-40-BE-en-10), §12.2files.sma.de ↗